Dissatisfaction expressed in Middlebury township over Canal & Construction Co.'s dredging of Maple River Drain, claimed not to meet specifications, but inspections by Commissioner Boutwell and Surveyor Joslin led to corrections, stump removal, and satisfactory completion of about 1.5 miles.
OCR Quality
Full Text
Dissatisfaction in Middlebury Over Construction, Says Ovid Paper.
Much dissatisfaction is being expressed on account of the alleged unsatisfactory manner in which the Canal & Construction Co., of Chicago, is doing the work of dredging the Maple River. It is claimed that in Middlebury township especially, the work is not according to specifications as to depth or width.
The county drain commissioner will soon look the work over and he says if he finds the dredging as it has been represented to him, the company will be obliged to go back and do certain portions over again.-Ovid Register-Union.
If the Register had waited to investigate it would have discovered that as soon as the poor work was called to the attention of Commissioner Boutwell he at once made a personal inspection as well as to order one made by County Surveyor Joslin. The result was that the Construction Co. was ordered to take its dredge back to the point where it was found that the drain had not been dug as wide as the specifications called for and to do the work properly. It was found that on one bank of the Maple a long row of trees had been cut down some years ago and the stumps were still in the ground and almost as solid as when the trees were standing. To avoid blasting these stumps the work was slighted. However, the stumps are out, the drain is fully as wide as the contract provides for and all parties are happy. Both Commissioner Boutwell and Surveyor Joslin state that the construction work on the drain has been done in good shape so far. About a mile and a half has been dug in Middlebury.
What sub-type of article is it?
What keywords are associated?
What entities or persons were involved?
Where did it happen?
Domestic News Details
Primary Location
Middlebury Township
Key Persons
Outcome
construction co. ordered to redo work where drain not wide enough due to stumps; stumps removed, drain now fully as wide as contract, all parties happy; about a mile and a half dug in middlebury.
Event Details
Dissatisfaction over Canal & Construction Co. of Chicago's dredging of Maple River Drain in Middlebury township, alleged not to meet depth or width specifications; county drain commissioner to inspect; however, Boutwell already inspected personally and ordered Joslin's survey, leading to company redoing work at deficient point due to unblasted stumps from cut trees; work now satisfactory per officials.