A report from the Engineer of the Wheeling and Belmont Bridge Company details the bridge's construction progress and costs, indicating advancement as expected or better, expenses below estimates, and completion within the set time and budget, including an extra $2,000 for railway fastenings.

Clipping

OCR Quality

98% Excellent

Full Text

WHEELING BRIDGE.

A report from the Engineer of the Wheeling and Belmont Bridge Company, to the managers, is issued from our press this morning by order of the managers, for general circulation. It shows the progress and cost of the work,—the progress to be as great as could possibly be expected, and the cost below the estimates.

The report shows that our highest expectations have been more than realized, sanguine as we are called, that the bridge will be completed within the time set, and within the estimates, even with the application of $2,000 dollars extra for railway fastenings.

What sub-type of article is it?

Infrastructure

What keywords are associated?

Wheeling Bridge Construction Progress Cost Estimates Bridge Completion

Where did it happen?

Wheeling

Domestic News Details

Primary Location

Wheeling

Outcome

progress as great as expected; cost below estimates; bridge to be completed within time and estimates, including $2,000 extra for railway fastenings.

Event Details

Report issued this morning details progress and cost of Wheeling Bridge construction by the Wheeling and Belmont Bridge Company; highest expectations realized.